Home > Select a State > CA > El Dorado County Air Quality Management District About EEA



Contact Information:

El Dorado County AQMD
2850 Fairlane Ct., Bldg. C
Placerville, CA 95667-4100
(530) 621-6662

Or view the Department's
Website

Relevant State
Agencies:

El Dorado County AQMD Regulations

California Public Utilities Commission

California Energy Commission

California BACT Clearinghouse Database

CARB Distributed Generation Program

Major Utilities:

Pacific Gas & Electric

Southern California Gas Company (SoCalGas)

Southwest Gas Company (SWGas)

Southern California Edison Company

Sierra Pacific Power Company

Pacificorp (Pacific Power & Light)

San Diego Gas Electric Company

El Dorado County Air Quality Management District-CALIFORNIA

AIR EMISSIONS REGULATIONS:

Air Quality Status Severe nonattainment for ozone (AQMD includes all of El Dorado County)
EPA's Nonattainment Areas
Major Source Threshold 25 tons of NOx or VOC triggers NSR
Minor Source Permitting Exemption Less than 50 hp or 3 MMBtu/hr or 2 lb/day
Minor Source Treatment BACT, PM and opacity 
Emergency Generating Limits 50 hours for maintenance and testing 

DE MINIMIS EXEMPTIONS (Must Meet 1298):

Engines less than 50 hp, turbines less than 3 MMBtu/hr and sources with uncontrolled emissions less than 2 lb/day of all pollutants are exempted from permitting.

MINOR SOURCE PERMITTING:

Sources with potential to emit greater than the following are subject to district BACT:

Pollutant Potential to Emit (lb/day)
CO 550
NOx 10
PM-10 80
VOC 10
SOx 80


The air district is likely to follow CARB's guidance for permitting of electric generating technologies. Sample BACT for control of NOx from turbines and internal combustion engines is as follows:

Size of Unit Level of Control (ppm)
>3 MW 9
3-12 MW simple cycle 2.5
3-12 MW combined cycle 5
12-50 MW simple cycle 2.5
12-50 MW combined cycle 5
IC Engines 9


Alternately, the air district may consider BACT used in the SCAQMD.

All units, regardless of size, must meet a 20% opacity limit and a PM limit of 0.1 grains per cubic foot.

The entire permitting process could take up to 180 days, but the district is currently backlogged so it could take the full 180 days or more.

TREATMENT OF EMERGENCY ENGINES:

Emergency engines must be permitted. Generally, these units will be limited to 50 hours for maintenance and testing and can only operate otherwise, during emergencies. Additional hourly limitations may apply on a case-by-case basis.

Get Acrobat Reader
Energy and Environmental Analysis Inc. | US DOE Distributed Energy Program | US EPA Air Quality Division | SiteMap/Search
Send Questions or Comments to Sean Mackay | © 2004 Energy and Environmental Analysis Inc., All Rights Reserved
1655 Fort Meyer Drive, Arlington, VA 22209