|
WHAT'S NEW:No recent state activity has been identified.AIR EMISSIONS REGULATIONS:
All new units not meeting the above exemptions must obtain a construction permit from the Public Service Commission (PSC). There have been several complaints to state officials that the fees charged by the PSC are prohibitively high. Fees are outlined in 26.11.02.16 through 26.11.02.19 of the state regulations. The PSC does not actually enforce limits, but does include the following requirements (which will be enforced by the Department of the Environment):
Sources that trigger Title V must also obtain a permit from the Department of the Environment. Additional fees will be required from the Department of the Environment. 250 tons of any criteria pollutant triggers PSD. 100 tons of NOx and 50 tons of VOC triggers NSR. In the severe nonattainment areas 25 tons of NOx or VOC triggers NSR. The NSR application should be submitted with the permit to construct application and must include emission controls that meet LAER and emission offsets which provide a net decrease in VOC and/or NOx emissions in accordance with the ratios listed under COMAR 26.11.17 for various geographical regions. Once a complete application is submitted it normally takes 10 months for approval. The guidelines state that it will cost exactly $20,200 to receive a permit to construct, which is required prior to NSR approval.TREATMENT OF EMERGENCY ENGINES Emergency generators can operate for up to 500 hours per year. In the past, emergency units were able to get a waiver if they agreed to operate for emergency use only, but still had to obtain a permit to construct. SITING REQUIREMENTS FOR NON-UTILITY GENERATORS: The state of Maryland witnessed a surge in CPCN applications in the late 1990's and early 2000's which raised concerns over the cumulative environmental impact of such plants. State authorities were particularly alarmed by the amount of proposed plants along the Potomac River in Maryland and Virginia. After the Enron scandal, many of these proposed merchant plants have been withdrawn due to tighter credit lending. In response to these concerns, a cabinet-level Task Force was convened by the Secretary of the Department of Natural Resources to develop a set of guidelines by which agencies would develop recommendations to the Commission on the power plant approval process. The Task Force released its findings in December 2002. The Maryland Power Plant Research Program (PPRP) evaluates power plant licensing requirements in the state, including the Certificate of Public Convenience and Necessity (CPCN) process. Information on Maryland's formal CPCN process and guidance documents can be found here. BUILDING, ZONING AND FIRE CODES:Building Codes: Maryland enforces the Maryland Building Performance Standards (MBPS). The MBPS adopts the 2006 IBC with some amendments. Each jurisdiction must use MBPS as its base, but may make local modifications. [1][2] Energy Codes: Included in the MBPS is the adoption of the 2006 IECC. This may not be modified by local jurisdictions except to make it more stringent. [1] Fire Codes: The 2008 Maryland Fire Prevention Code, which applies statewide except in Baltimore, is based on NFPA’s 2006 UFC. Zoning: Zoning and planning happens at the local level. Some restrictions are enforced for specific types of land (i.e. resource protection) by state code. Check with each jurisdiction regarding their zoning codes. Resources (information may not be as current as provided above) A general overview of each state’s enacted codes can be found HERE. The International Code Council Adoption page gives state-by-state adoption status of specific ICC codes, as well as information about code adoption by some municipal governments within that state. Information about energy codes can be found at the DOE’s Building Codes for Energy Efficiency page Maryland’s final interconnection rules became effective June 9, 2008. The rules apply to all utilities and all distributed generation systems of less than 10 MW. Determining what type of review is necessary to connect a system to the grid first requires the system be classified in one of four levels:
Lab-certified equipment is defined to mean equipment tested and approved by a nationally recognized testing laboratory (NRTL) as being in accordance with IEEE 1547, UL 1741, and the National Electric Code (NEC). Field approved systems are generally non-certified systems that have been tested and approved under a prior review by a utility, subject to certain other restrictions. Utilities may not charge any processing fees to Level 1 applicants and processing fees are limited to $50 plus $1/kilowatt (kW) of capacity for Level 2 requests and $100 plus $2/kW of capacity for Level 3 and 4 requests. Utilities are also required to designate a contact person and provide assistance materials on their website for use by prospective applicants. Standardized interconnection agreements will be available for all levels of interconnection request. The issue of insurance requirements is not addressed; however, Maryland’s net metering law prohibits utilities from requiring additional liability insurance for net metered customers. The information provided here is a basic summary. For more specific and detailed information consult the interconnection rules or contact the Maryland Energy Administration. Tim LaRonde EXIT FEES:There are no explicit exit fees in Maryland. However, some utilities have still been able to recover their stranded costs. DG owners have to pay for upfront costs related to receiving service. The MD PSC has a policy that utilities can't "socialize costs," meaning that costs cannot be passed along to other customers. Maryland does not have a statewide policy on standby rates. Related policies for Maryland utilities are listed below. Potomac Edison Co. (Allegheny Power )
|
||||||||||||||||||||||||||||||||||||
Energy and Environmental Analysis Inc. | US DOE Distributed Energy Program | US EPA Air Quality Division | SiteMap/Search Send Questions or Comments to Jessica Rackley | © 2008 Energy and Environmental Analysis Inc., an ICF International Company, All Rights Reserved 1655 Fort Myer Drive, Arlington, VA 22209 |
|||||||||||||||||||||||||||||||||||||