|
WHAT'S NEW:No recent state activity has been identified.AIR EMISSIONS REGULATIONS:
The following are exempt from obtaining permits: Internal combustion engines used for standby service, including compressors and pumps used for emergency replacement and portable generators as follows: External combustion sources listed below are exempt from permitting: Emission units with uncontrolled emissions of less than 5 tons per year of NOx, SO2, or PM10 are also exempt from obtaining permits. Further information on insignificant activities can be found here, http://www.deq.state.va.us/export/sites/default/air/pdf/airregs/804.pdf. State BACT is required for all minor sources and all criteria pollutants. The state does not have a cost threshold established, but a source can take operating or fuel limits to avoid controls. There is an opacity limit of 20%, except for one six-minute period within any hour of not more than 30% opacity. A potential to emit 250 tons (100 tons for listed sources) of any criteria pollutant triggers PSD in attainment areas. In the nonattainment areas classified as moderate 100 tons of NOx or VOCs triggers NSR. · 2.5 ppm or less for natural gas TREATMENT OF EMERGENCY ENGINES Engines and turbines used for emergency purposes only and which do not exceed 500 hours of operation per year at a single stationary source are exempt from permitting if they meet the following requirements:
Emergency units can operate only during interruption of power from the utility or during brief maintenance and testing exercises. The unit must document operation and notify the state in order to qualify for this exemption. Also, emergency generators in the Northern Virginia Region may be required to obtain a permit since this area is a nonattainment region. Emergency generators in this Region are evaluated based on a pte of 8760 hours per year operation. If the pte is greater than 25 tpy of NOx a permit is required and a RACT evaluation is conducted. “Non-emergency generators” are units used for peak shaving, distributed generation, or for generating electricity for any reason other than emergency use explained above. A non-emergency generator has a pte based on 8,760 hours and thus will likely require a permit regardless of size. See the following webpage for more information about emergency and non-emergency generator requirements, http://www.deq.state.va.us/air/permitting/egrequirements.html.SITING REQUIREMENTS FOR NON-UTILITY GENERATORS: In the state of Virginia, the State Corporation Commission regulates the siting of electrical generation facilities over 50 MW. However, the Commission specifically exempts distributed generation from these requirements. BUILDING, ZONING AND FIRE CODES:Building Codes: Virginia enforces the 2006 Virginia Uniform Statewide Building Code, which references the 2006 IBC with some amendments. Local jurisdictions may not make amendments. Energy Codes : Virginia enforces the 2006 Virginia Uniform Statewide Building Code, which references the 2006 IECC with some amendments. Local jurisdictions may not make amendments. Fire Codes: Virginia enforces the 2006 Virginia Statewide Fire Prevention Code, which references the 2006 IFC with some amendments. Local jurisdictions may not make amendments Zoning: Zoning and planning happens at the local level. Check with each jurisdiction regarding their zoning codes. Resources (information may not be as current as provided above) A general overview of each state’s enacted codes can be found HERE. The International Code Council Adoption page gives state-by-state adoption status of specific ICC codes, as well as information about code adoption by some municipal governments within that state. Information about energy codes can be found at the DOE’s Building Codes for Energy Efficiency page or at the Building Codes Assistance Project.Current standards under the Virginia State Corporation Commission (SCC) only apply to systems that are net-metered. The SCC is currently working on developing interconnection standards for DG systems that are not net metered. In May 2000, the Virginia Corporation Commission (VCC) issued an order establishing interconnection requirements for net metering customers with residential generators less than 10 kW or nonresidential generators less than 500 kW that use solar, wind, or hydro energy. These standards were enacted with Va. Code § 56-578 and then later with 20 VAC 5-315-40. On August 8, 2006, the VCC (Case #PUE-2006-00064) rejected using federal (EPAct 2005) interconnection rules, and said it will (continue to) develop its own statewide standards. Virginia expanded net metering with the passage of HB 1541 in April 2006. All renewable energy systems that generate electricity are now allowed to net meter. Renewable energy is defined in the state as "energy derived from sunlight, wind, falling water, sustainable biomass, energy from waste, wave motion, tides, and geothermal power." The new legislation also allows net metering for customers who contract with other entities to own or operate net-metered systems. Previously, systems had to be located on a customer's property. Virginia residential customers with systems up to 10 kW and nonresidential customers with systems up to 500 kW are allowed to net meter. A utility may require a manual, external disconnect switch be installed. Generators that meet National Electrical Code (NEC), Institute of Electrical and Electronic Engineers (IEEE) Standard 1547 (July 2003), and Underwriters Laboratories (UL) safety codes do not need additional safety equipment. Systems with up to 10 kW rated capacity must have a minimum of $100,000 liability insurance; systems with greater than 10 kW must have at least $300,000. For more information contact your electric distribution utility or the Virginia SCC. Virginia State Corporation Commission Division of Economics and Finance Tommy Oliver EXIT FEES:There are exit fees for DG in the state of Virginia. SB 1416, passed in 2007 governs exit fees and other utility policies. Just and reasonable net stranded costs, to the extent that they exceed zero value in total for the incumbent electric utility, shall be recoverable by each incumbent electric utility provided each incumbent electric utility shall only recover its just and reasonable net stranded costs through either capped rates as provided in § 56-583. To the extent not preempted by federal law, the establishment by the Commission of wires charges for any distribution cooperative shall be conditioned upon such cooperative entering into binding commitments by which it will pay to any power supply cooperative of which such distribution cooperative is or was a member, as compensation for such power supply cooperative's stranded costs, all or part of the proceeds of such wires charges, as determined by the Commission.For DG units seeking standby service, “Schedule 8: Supplementary, Maintenance, Standby Service For Customers with Power Plants” applies.
|
||||||||||||||||||||||||||||||||||||||
Energy and Environmental Analysis Inc. | US DOE Distributed Energy Program | US EPA Air Quality Division | SiteMap/Search Send Questions or Comments to Jessica Rackley | © 2008 Energy and Environmental Analysis Inc., an ICF International Company, All Rights Reserved 1655 Fort Myer Drive, Arlington, VA 22209 |
|||||||||||||||||||||||||||||||||||||||